A construction change order documents an agreed modification to the work, contract sum, contract time or other contract terms. The project agreement determines who may request, price, review, authorize and sign a change; it also determines whether work may proceed before final agreement.
This guide explains common change-order types, documentation, pricing inputs, schedule review and approval controls for commercial construction owners. It does not replace the project’s contract.
What is a Change Order in Construction?

A construction change order is a document that specifies an amendment to the original contract between the owner and contractor (or a contractor and a subcontractor) and other project stakeholders (architect, engineer, etc.).
It may document changes to scope, drawings, specifications, materials, compensation, milestones or contract time. The required form, signatures and authorization path come from the executed construction contract. Some contracts also distinguish agreed change orders from directives, minor changes, allowances, unit-price adjustments or time-and-material authorizations.
Construction change orders generally involve:
- Introducing additional work, known as additive change orders
- Removing portions of scheduled work, known as deductive change orders, and
- Substituting work to create the best possible result
For example, if an owner decides to upgrade from standard cubicle partitions to glass partitions or when a contractor wants to substitute specified materials with alternatives due to availability issues, the contractor drafts a construction change order to formalize these adjustments. Depending on the size of the change, there may be alterations to the contract terms or amount.
Change-Order Provisions in the Contract
Do not copy a generic clause without project-specific review. The agreement should be checked for:
- who has authority to request and approve a change;
- required notices, supporting records and submission deadlines;
- pricing methods, allowable markups, credits and time-impact requirements;
- whether disputed or emergency work may proceed before agreement; and
- the signatures or other evidence required for authorization.
Types of Construction Change Orders
In construction projects, change orders are official modifications to the original contract. They can arise from design changes, unforeseen site conditions, or even errors. Here are the three main types of change orders, each with its own cause and process:
-
Additive Change Order
These increase the project’s scope, cost, or timeline. For example, the scope of a tenant improvement project might change to include a new conference room or upgraded HVAC system. This requires adjusting budgets and schedules. An additive change order formalizes the added work and ensures everyone is aligned before moving forward.
-
Deductive Change Order
Deductive change orders reduce the scope or cost of the project. For example, in a commercial office build-out, the client may choose to eliminate custom millwork in break areas and opt for standard cabinetry instead, to stay within budget. This type adjusts the contract price downward and may speed up completion if work is reduced.
-
Substitution Change Order
A substitution change order involves swapping one material or method for another. For instance, a contractor might suggest switching from curtain wall glazing to precast panels to speed up installation. Though the change doesn’t always affect the cost, it still needs approval and documentation to avoid disputes later.
Four Common Change-Order Pricing Approaches

A change can be priced in several ways. The contract—not a generic rule—controls which method is permitted, what records are required and how overhead, profit, bonds, insurance, taxes, credits and schedule impacts are handled.
-
Lump Sum
A fixed sum or lump sum change order contract is requested when the alteration in the work scope can be quantified with a firm price. Lump sum change orders can define adjustments in the cost, including direct and indirect costs, markup, and contractor’s profit. This results in an overall increase in the project expenses or adds credit to the contract value.
-
Zero Cost
This type of change order does not affect the contracted price. It is used to document scope-of-work changes that may not affect the contract value but impact the project schedule. For example, the contractor suggests installing energy-efficient LED lighting instead of fluorescent fixtures (price remains the same), which can delay the project but help increase client satisfaction.
-
Time and Material (T&M)
A time and materials (T&M) contract for a change order occurs when the entire cost of the proposed change is unknown. Here, contractors track their time spent working on the alteration and costs associated with labor, materials, or equipment. The client can ask for a breakdown of these expenses to justify the construction change order costs.
-
Unitary Cost
A contractor negotiates this type of change order contract upfront before any change-related work starts. The contractor tracks an additional scope of work based on specific measurement units. Meaning, they are already familiar with these scopes of work. For example, painters will have a unitary cost change order for applying a type of paint finish selected by the client.
A hybrid approach combining time and materials (T&M) with a lump sum change order entails initially handling modifications on a T&M basis and then negotiating a fixed sum based on finished work.
Thus, identifying the type of construction contract allows parties involved to determine a process for making changes to the project’s scope.
When Do Construction Projects Need Change Orders?

Change orders are common, but they are not a fixed percentage or a substitute for planning. Clear scope, existing-condition review, coordinated documents and timely owner decisions can reduce avoidable changes, while concealed conditions, agency requirements, availability, design development and owner requests may still require contract adjustments.
There are various reasons for a general contractor or an owner to request change orders during a construction project. Some of the major causes include:
- Difference in site conditions: Sometimes the job site conditions are different from those identified in the contract documents. For example, a slope that requires leveling, uncleared vegetation, etc. To accommodate these changes, changes to the original plans are necessary.
- Owner-requested changes: The owner or client may request design modifications to the original plans or specifications, such as incorporating or removing a fixture. They may also direct the contractor to make changes to the project’s budget or schedule.
- Design errors or omissions: Construction change orders for design errors or omissions address defective or missing items or specifications mentioned in the original contract.
- Material or equipment availability: If a construction material or equipment is unavailable due to supply chain issues or increased market prices, it may force the contractor to alter the originally planned resources.
- Change in design standards: There may be an upgrade in design standards or an inspector may require additional work before approving building permits.
- Delays in schedule: Due to unforeseen events like labor shortages, internal disputes, or extreme weather conditions, the project schedule may need significant modifications.
- Task sequencing: The owner may request the construction team to prepone or postpone a specific task, for example, finishing the interior of the meeting room before the reception area. Such an improvement in the planned schedule may require issuing a change order.
- Inaccurate cost estimates: If the contractor has underestimated the cost of materials, for example, the cost of a standard plywood sheet of 8 feet hikes from $50 to $70, the budget may require changes to accommodate extra costs.
- Misleading Contractor Bids: Often, construction contractors submit lowest possible bids to secure the contract. But addition of work items to the original scope during the project may result in expensive construction change orders.
- Subcontractor issues: Problems with subcontractors or their unavailability can lead to unexpected issues, which need contractors to request change orders.
- Inadequate Funding: Large commercial construction projects often experience cash flow problems due to a lack of loan lenders, necessitating alterations to the scope.
Regardless of the reasons behind issuing a change order, open dialogue between the owner and the construction company greatly helps to lessen the negative impacts of the adjustments on the project.
What Should You Specify in a Change Order Form?

A change order form is a document used to officially request changes to a project’s scope, specifications, or other contractual elements.
Change orders vary depending on the project, stakeholders involved, and changes requested by one or both parties. At a minimum, all construction change order forms should specify the following:
- The name, location, and original contract number of the project
- The name, address, and contact information of the project’s owner, contractor, and architect
- The licence number of the contractor submitting the change order
- Change order number
- Description of the requested change in comparison to the original contract or contractor bid
- Justifying documentation such as construction drawings
- The price of the requested change (breakdown of the costs as well as the total)
- Itemized subcontractor costs
- A contractual statement specifying how the requested change impacts the project completion date, price, and payment terms
- The signatures of the client, contractor or subcontractor, and all necessary representatives like architects or engineers
- The date for initial change order request, the creation of the official document, when it was signed by all necessary representatives (and other relevant third parties), and when the initial request was received by the counterparty
- The revised contract amount upon approval and project completion date
Because a signed change order may modify the contract, its scope, pricing, time impact, assumptions, exclusions and authorization should be accurate and reviewed under the agreement. Legal review may be appropriate for disputed, material or unclear changes.
The American Institute of Architects (AIA) provides the AIA G701 Change Order form, a standardized AIA form used within the applicable AIA contract framework; it does not by itself establish compliance or authorization.
Examples of Change Order Scenarios During a Construction Project

The correct document depends on the contract and facts. Common commercial scenarios include:
- Owner-requested scope: The owner adds a conference room or changes an approved finish after the original scope is established.
- Existing conditions: Authorized demolition exposes a condition that differs from available documents and requires design-team direction.
- Agency or landlord direction: A reviewing authority or landlord requires a documented revision to the approved project approach.
- Material or equipment availability: A specified item becomes unavailable and the team evaluates a proposed substitution, including cost, time and performance implications.
- Owner-equipment coordination: Revised vendor criteria change power, plumbing, structural support, clearances or delivery sequencing.
An RFI, proposal request, architect’s instruction or field observation is not automatically a change order. The contract determines when the issue becomes an authorized contract modification.
Samples of a Change Order Template

Change Order Template in Word legaltemplates.net/

Change Order PDF Template Smartsheet PDF

Time and Materials Change Order Excel Template Levelset
Steps to a Smooth Change Order Process
The change order process begins with identifying a deviation from the original project scope, timeline, or budget. Once the change has been identified, it’s time to take approvals from all parties involved. From initiation to approval, a typical construction change order process follows a step-by-step progression that looks like:

Step 1 – Review the Contract and Project Specifications
The first and foremost step you should take before proceeding with the change order process is to thoroughly examine your contract and project plan.
Review the executed contract for the change procedure, notice deadlines, documentation, pricing basis, schedule analysis, authority and required approvals. If the agreement is silent or unclear, obtain project-specific professional guidance rather than relying on an online template.
Next, have a clear understanding of your construction plans and specifications. Identify any vague information or errors in the scope of the project that should be rectified. This will help avoid expensive, surprise construction change orders later. If needed, clarify your doubts from clients, architects, engineers, or subcontractors regarding the work details.
Step 2 – Discuss the Change with Stakeholders
Contractual agreements require modifications due to various reasons including owner-initiated changes, material supply issues, design errors, unsuitable site conditions, and others.
The participants identified by the agreement should review the proposed scope, cost and time effects. Discussion improves alignment, but contractual approval must come from the parties with designated authority.
Step 3 – Create a Change Order Request
Now it’s time to make the change official. Once there’s an agreement on the scope, schedule, and budget, the contractor drafts a formal “change order request” to be signed by all parties. The general contractor submits this request typically using a special change order form template, mentioning:
- Business information
- Detailed description of the proposed change
- Construction drawings
- Impact on timelines
- Price quotation for extra work
- Revised payment terms and other vital elements
Ensure your construction change order request clearly outlines price and timeline revisions, and if there are no alterations in either of these, mention that as well. Submit the prepared change order request to all project stakeholders for review.
Step 4 – Negotiate an Agreement on Change Order Proposal
It is possible that some stakeholders may have disagreements over adjustments like extension of schedule or design updates requested by the initiating party. This is the stage when all parties engage in negotiations to reach mutually acceptable terms for a smooth change order process.
Negotiate the price and schedule of change orders using unit prices, lump sums, cost-plus, or time-and-material (T&M) techniques. Consider the value and quality of the work, market conditions, and your relationship with the other party.
Assess the technical, operational, and legal feasibility of construction change orders, identifying any potential issues for the future. Aim to make a unanimous decision that satisfies both parties’ interests.
Step 5 – Get the Change Order Signed
The recipient finally reviews the change order proposal. A Request for Information (RFI) can be issued to ask for additional information. Once everyone agrees on the proposed change including the owner, all parties sign the formal construction change order document to amend the original contract.
Many contractors, fearing delays and subsequent increased costs, start the revised work without waiting for the owner’s approval. This move can backfire if the owner decides to alter or reject the change order request.
After the official sign-off, the general contractor and subcontractors notify all construction workers of the approved changes.
Step 6 – Record in Your Change Order Log
Though the last step of the construction change order process, documentation is an integral part that general contractors should not neglect. They should register all approved change orders in a change order log for invoices/payments, dispute management, or audits. Tax laws depending on your location may require you to keep these records for a few years to more than a decade.
When all communication between the owner, contractor, subcontractors, and other participants is documented throughout the construction change order process, it helps to avoid unnecessary disputes. You can find free change order log templates online for effective document management.
How to Estimate Change Orders in Construction
A defensible change-order proposal connects quantities, rates, records and schedule effects to a clearly described scope. The contract controls allowable costs and markups. A practical review normally addresses the following categories.
1. Added and Deleted Direct Work
- labor classifications, hours, wage rates and contract-allowed burdens;
- material quantities, supplier quotations, delivery, storage and applicable credits;
- owned or rented equipment and the supporting rate basis;
- subcontractor proposals, lower-tier support and deleted-work credits; and
- design, testing, permits or vendor work only when assigned and compensable under the agreement.
2. Indirect and Contract-Allowed Additions
Field supervision, temporary facilities, extended conditions, bonds, insurance, taxes, overhead and profit should not be added from an internet rule of thumb. Identify the contractual basis, calculation method and supporting records for each item.
3. Schedule and Sequence Effects
State whether the change affects procurement, access, shutdowns, inspections, milestones or critical-path work. A requested time adjustment should distinguish the added work’s duration from its effect on contract completion and should follow the schedule-analysis requirements in the agreement.
4. Assumptions, Exclusions and Validity
Record drawing references, site assumptions, proposal validity, escalation treatment, working hours, access, owner-furnished items and exclusions. This lets reviewers see what would change if an assumption proves incorrect.
5. Reconciliation and Approval
Compare the proposal with the owner or design team’s independent review, resolve scope gaps, document agreed cost and time effects, and obtain the authorization required by the contract before proceeding—unless the agreement provides another written direction for the specific circumstance.
Using Change Order Software for Streamlining Workflows
While the manual process is standardized, submitting and approving change order requests on paper, via email, or by phone can be time-consuming. Instead, construction change order software and automation streamline change order form creation, management, and approval processes.
With platforms like Procore or Autodesk Build, contractors, owners, and subcontractors can use a shared dashboard to submit, carefully review, and approve changes in real time. Plus, these digital tools automatically link change orders to the project schedule and budget, reflecting any changes instantly. It saves time, reduces errors, and keeps the entire team on the same page.
Construction companies can establish tailored workflows, for example, an owner or contractor issues a request for improvements, fill out the form, and sign off the document. The recipient immediately gets notified about the pending request awaiting their signatures. Once signed off, the document is safely stored in the platform for future reference.
Here are ten construction management software with change order management features:
- Contractor Foreman
- QuickBooks
- Desktop Enterprise
- Autodesk Construction Cloud
- Smartsheet
- Procore
- CoConstruct
- Wrike
- InEight
- Fieldwire
Directives, Minor Changes and Disputes

Not every project uses the same document family. Under AIA-based agreements, a change order, a Construction Change Directive and an Architect’s Supplemental Instruction can serve different functions. Other contracts use different names and authority structures.
Agreed Change Order
AIA’s G701 change-order resource describes a form for changes agreed by the owner, contractor and architect, including adjustments to contract sum and contract time. That description applies only when the project uses the relevant AIA documents and has not modified them in a way that changes the process.
Construction Change Directive
A Construction Change Directive is not a general right to force any requested work on any contractor. Whether a directive is authorized, who may issue it, how work is priced and how disagreement is preserved depend on the executed agreement. Under the relevant AIA framework, an agreed adjustment arising from a directive is later recorded by change order.
Architect’s Supplemental Instruction
An Architect’s Supplemental Instruction may document a minor change in projects using the applicable AIA documents. The project team must still determine whether the instruction affects cost, time or scope and follow the contract if it does.
When the Parties Disagree
Preserve notices, daily records, RFIs, drawings, quotations, labor and equipment records, schedule analyses, meeting minutes and reservation-of-rights communications required by the contract. Do not rely on this guide to determine entitlement, waiver, damages, dispute procedure or whether work must proceed. Those questions require the executed documents and, when appropriate, legal advice.
Best Practices for Managing Change Orders
A disciplined change process improves visibility and decision quality. It cannot guarantee that a project will avoid cost, time or dispute impacts, but it can make the basis of each decision easier to review and administer.
1. Establish a Change Order Policy Upfront
From the start of the project, ensure your construction contract includes a clearly defined change order procedure. This should outline how changes are identified, documented, approved, and incorporated into the project. A clear policy minimizes confusion and ensures consistency across all parties.
2. Use Standardized Forms and Templates
Utilizing standardized change order forms helps maintain uniformity and ensures all required details are captured—such as the reason for the change, scope adjustments, cost impact, and revised timelines. Tools like Procore or Buildertrend offer built-in templates that streamline this process.
3. Maintain Thorough Documentation
Every proposed change should be backed by solid construction project documentation, including drawings, emails, RFIs (Requests for Information), site photos, and meeting minutes. These records serve as evidence in case of disputes and support accountability throughout the change order process.
4. Communicate Early and Often
As soon as a potential change is identified, communicate it to all stakeholders. Delayed communication often leads to unauthorized work or misunderstandings. Regular project meetings should include a review of pending and approved construction contract changes.
5. Use Technology to Streamline Change Orders
Adopt construction management software to track change orders in real-time, automate approval workflows, and integrate changes into schedules and budgets. These platforms improve visibility and reduce the administrative burden.
6. Plan for Contingencies
Establish owner-held contingency based on scope maturity, existing-condition uncertainty, market conditions, procurement and the project’s risk review. Do not treat contingency as permission to perform unapproved work or as a universal percentage.
By following these best practices, contractors and project owners can pull off change management more effectively, reducing risk, delays, and cost overruns while keeping the project on track.
Owner’s Change-Order Review Checklist
- Is the changed scope clear and tied to current drawings, specifications or field information?
- Does the request identify why the change is needed and who initiated it?
- Are added work, deleted work, credits, markups and supporting records visible?
- Are schedule and milestone effects stated separately from cost?
- Are assumptions, exclusions, proposal validity and outstanding decisions documented?
- Has the person with contractual authority approved the correct document?
Constructive Solutions is a San Francisco Bay Area commercial general contractor. Our preconstruction services emphasize defined assumptions, budget basis, decision tracking and schedule coordination. Review our documented commercial projects or discuss project fit with the team.
FAQs
Who manages construction change orders?
The contract and project organization determine responsibility. An owner representative, architect, construction manager, contractor or project manager may administer part of the process, but only designated parties have authority to approve contract changes.
What is an acceptable change-order percentage?
There is no universal acceptable percentage for change frequency, value, contingency or markup. Compare each request with the contract, approved scope, supporting records and project-specific risk allocation.
Is an RFI a change order?
Usually not. An RFI requests clarification or information. The response may reveal or direct a scope, cost or time effect that must then follow the contract’s change procedure.
What percentage of projects have change orders?
Rates vary by project type, study method and the definition of a change. A generic industry percentage is not useful for pricing or approving a specific project.
What is an ASI in construction?
In projects using the applicable AIA documents, an Architect’s Supplemental Instruction may document a minor change. The team must evaluate whether it affects cost, time or scope and use the contract’s change procedure when it does.
What is the construction change process?
A typical process identifies the issue, checks contractual notice and authority, defines scope, prices added and deleted work, evaluates time impact, resolves assumptions, obtains required approval and records the result. The executed agreement controls the actual sequence.
What is the difference between a change order and T&M?
A change order modifies or records a contract change. Time and materials is a pricing or recordkeeping method that may be used for changed work when the contract authorizes it.
Relevant Resources:
Constructive Solutions, Inc. is a full-service commercial construction company serving San Francisco and Bay Area.
Whatever your vision, we have the resources, experience, and insight to make your concept a reality, and a space where your business can flourish.
Call Us Now for Estimate











Leave a Reply